KG-13 (PONTUS)
The KG-13 Electronic Key Generator, Transmitter/Receiver was similar in appearance to the KG-14. This solid state design dating from the mid-to-late 1960's, originally cost $US 40,000 per copy.  It was one of the first crypto machines to encrypt data such as facsimile. Crypto technicians received 10 to 12 weeks training on the machine.  The KG-13 was comprised of a KG-3 transmitter and a KG-12 receiver.
 
kg13_3drawer_view.jpg
A KG-13 unit. One drawer bears the designation KGD-3/TSEC.  The total weight is around 250 pounds. (Photo courtesy Bill Rhoads, BGR101(a)aol.com)

The KG-13 was controlled by "key cards". These were IBM-like punch cards that determined the starting point of the KG-13 encryption which was done by "koken stages". The key cards were changed daily at HJ time. When the USS Pueblo, with a live KG-13 aboard, was captured by the North Koreans in 1968, the personnel didn't have time to destroy it. As a result, a working model of the KG-13 fell into enemy hands. NSA quickly designed a modification to the koken stage board to alter its operation in order that the enemy didn't have an identical working model.

CARD READER DESCRIPTION

Select this link to see the inside of the card reader.  Ronald Coppock, who worked with the KG-13 indicates that it was fitted with a card cutter and also without.  "In Ethiopia, I worked at two locations (Stonehouse and Tract C)  that had KG13's equipped with the KW26 style card cutters. All the machines at Stonehouse were equipped that way and about 20% at Tract C. At the 7th Radio Research in South East Asia, about 30% of the KG13's had the card cutter style card readers. 13's equipped with the card cutters were operated on very high priority circuits with short cycles to change key material. Some were on 6 hour and others on 12 hour cycles".

The KG-13 did have a major difference in that in its latter years,  it was equipped with a Card Reader Insert Board or CRIB.

INTERNAL DESCRIPTION

The KG-13  employed  "FLYBALL" modules. These were modules comprised of discrete components set up as logic element circuit groups such as AND gates, OR gates, FLIP FLOPs, Inverters etc.  Once tested, the modules were potted in a compound whose colour indicated functionality. The coloured potting compound was extremely hard and any attempt to penetrate it resulted in damage to the internal circuitry.

In a KG-13, the following colours are confirmed: Pink, Yellow, Green, Blue, Red, Orange and Black. Purple and Brown modules were probably used but those colours are unconfirmed as of this time.

Failures usually occurred in the power supplies, buffers, and synchronizers though most problems were quickly resolved. When new, there was a high frequency of failures due to cold solder joints.

One board in the KG-13 had a black module which was a noise generator. Repair depot technicians were told it was the only module which was classified because the noise from a diode was used to generate a random key stream used in the encryption process.

The circuitry inside the module then used the koken chains to create an extremely random key stream.  That was why there was no problem in restarting the KG-13 with the same card. The noisy diode ensured that the chances of duplicating the start point was not measurable by any standards known at the time.

Two of the key cards were for the transmitter and the third for the receiver.  There were two for the transmitter because it had two key generators.  The keystream mixed with the plain text produced the ciphertext.  Two key generators generating the same keystream should match bit for bit at the output and a mismatch would cause a crypto alarm and a shutdown of the output.  A key generator failure would stop transmission and prevent a compromise.  With only a single key generator in the transmitter a failure could produce a trivial keystream (all one's, all zero's or alternations).  A receiver key generator failure just produced garble. The KG-3 could be used to transmit or receive since there is a XMIT/RECV switch on in the lower right hand portion of the lowest unit.

In the 1964/65 time frame, crypto techs were taught that it would take 50,000 years to break the key on a KG-13 using state of the art techniques which were available at the time. The KG-13 also employed traffic flow security.
 
 

kg13_board_drawer.jpg
A side profile of one drawer. (Photo courtesy Bill Rhoads, BGR101(a)aol.com)

 
kg13_pink_core_boards.jpg
An internal view of one of the drawers showing the potted component technique. (Photo courtesy Bill Rhoads, BGR101(a)aol.com)

Steve Gardner recalls "One of our operations sites which monitored satellites used an item called a "shark" between the teletype and the KG-13.   It was a block message transceiver".

The KG-13 device was taken out of service around 1989-90. This was one of the last discrete component crypto machines built.  Shortly after this time, integrated circuits started to appear in crypto machine designs.

Also refer to Fascinator for complementary information.

A Young Airman’s Experience with the HN-1 Modem
By Jim Hartle

Though the HN-1 was not a piece of crypto equipment, it was near and dear to most Airmen going through the Air Force Crypto School at Lackland AFB in the mid 1960s.  The HN-1 was a one drawer modem device that could be set to work either send or receive but only one way at a time.  They were used in conjunction with the KG-13 to run some data circuits.

The basic course in 1965 consisted of electronic fundamentals, the HN-1 and then the KW-26 and the KG-13.  The HN-1 was used as a beginner piece of equipment to allow the trainees to “get some experience on real equipment”.  The instructor told us over and over that it was obsolete and “we would never see it in the field” - famous last words.

As enterprising young Crypto trained killers we all promptly forgot everything we learned about the HN-1 after we tested the block because, “we would never see it in the field”.   If I remember right we also went on our first leave after the HN-1 and then returned for the KW-26 and KG-13.

After school I was assigned to Wheeler AFB Hawaii.  I was mis-shipped to Wheeler.  I was really supposed to go to Wheelus AFB, Libia, North Africa but that is a whole other story.

When I arrived the NCOIC, MSgt Tommy L. Holland, ask me if I was trained on the HN-1 and I told him I was, but that it was an obsolete piece of equipment and no longer in the field.  WRONG!  He said “there are four of them in the back room” and “you’re the only one that has had any training on them”!  Further he went on to tell me that, one only worked in transmit, one in receive only, one worked both ways (sort of), and the fourth didn’t work at all.  He then went on to explain that my upgrade to a 5 Level hinged on the repair of the all four units.  We were allowed to keep our training material about the HN-1 when we left Crypto School, because it was unclassified, and for some reason (maybe the providence of Divine intervention) I still had them.

At Wheeler the HN-1 was used on a half duplex Autodin circuit to Hickam AFB using a KG-13, HN-1 modems and a Cubic with a 026 card punch and reader.

The HN-1 was made up of miniaturized vacuum tubes much like the type on the KWR-37.  Some were plugged in but most were soldered to the circuit boards.   I started with  the dead one since I was scared to touch the only operational spare equipment.  It took me about three weeks of constant work to unsolder and test each tube that looked suspicious (no glow).  I replace dozens of them and finely got it to where I thought it was operational both send and receive.  All this time MSgt Holland would stick his pipe-clenching face around the corner, once a day, followed by his head and ask how it was going.  I told him just fine and kept testing tubes.

Since it was only a half duplex circuit, testing the modem was a long affair with begging for down time to cable them up and reset the circuit and test.  Upon completing the repairs on the first HN-1 and proving that I had a little bit of maintenance ability MSgt Holland was anxious to get all of them operational both send and receive and be able to call the complete system operational.  A total of six months elapsed before that goal was attained and literally 100s of vacuum tubes unsoldered, tested, and replaced and soldered back in.

When I was finished repairing the HN-1s, and had my CDC (Career Development Course) course finished, I was recommended to see the evaluation board for recommendation take my SKT (Skill Knowledge Test).  I passed the board took the SKT, passed it and got my 5 Level.  I learned a lesson and never again believed the phrase “You’ll never see this again”.



Contributors:

1) Thoms Forbes <Thomas.Forbes(at)L-3com.com>
2) Lee K. Shuster, Salt Lake City, Utah
3) Steve Gardner.  E-mail: steveg(at)dfa-inc.com
4) Fred Schroeder <mail3(at)schroeder-family.us>
5) Doug Eyre
6) Jim Hartle  < Hartle1(at)aol.com>
7) Ronald Coppock,  Bakersfield CA<rwcoppoc(at)pacbell.net>
 


Back To Menu Page

Feb 16/10